Photo's of Fire Hall #2 (Meadowood)
as Construction progress.

 

Should any member wish for a larger version of any of these photo's
please contact the Web Master

February 10th, 2009

Ground breaking took place today in the snow.
The honour of putting the first shovel on the ground went to Lou Biggeman the RDN area representives accompanied by Joe Stanhope and Dave Bartram

 

Members of the Dashwood Fire Department, the Meadowood Steering Committee were also present together with Nancy Avery & Carol Mason from the RDN

 

 

DASHWOOD FIRE HALL #2
to be located at 1800 Galvin Place, off Meadowood Way.

Building Color Scheme



Floor plans.

 


Work on the Fire Hall Construction site commenced today February 12th, 2009
To see the photo's as things progress please scroll down slowly to the various stages.

 

PLEASE NOTE IMPORTANT INFORMATION

See Next Item

The Construction Site is off limits to all unless permission has been granted by the Site Superintendent and you must be wearing full safety gear. Hard Hat, Hi-Vis Clothing and Steel Toed Boots as per WCB.

 





   

Work on site was held up due to weather conditions the contractors were supposed pour concrete for the walls today but this has been delayed 24 hrs



 

 

 

All under ground plumbing and electrical conduits within the building structure are now in place as of Friday 6th of March.
The sewer lines and other lines were filled with water for testing with the aid of the fire department tanker truck.

Monday 9th March, the first of two loads of the steel building arrived today, the remainder finally arrived mid-afternoon Wednesday March 11th.


Erection of Steel Frame work commenced mid-afternoon Thursday 12th March.


While the erection of the steel work continues entrance to the site has been move
approx 60 feet west, to provide level entry onto the road.
Next will be the re-alignment of the road within the site.

Re-alignment of road started on Monday 23rd, March

New Access Road completed Tuesday 24th, March.


 However at the end of June we had to lower the road to match the front forecourt.

 

     

Grading of the site slopes commenced to day Saturday 14th, March

   
     

It snowed again over Sunday and Monday night 15/16th March,
 

Framing of the wood section started today Monday 23rd, March

Steel Erectors commence installing the walls to-day Wednesday 25th, March


The plastic membrane for water proofing the floor, then the re-bar mat is being put into place.

The floor is honeycombed with electrical conduits, note the grey plastic lines.

This means nothing can be bolted down to the concrete floor.


The start of the roof installation

Internal Colour scheme

April 8th, 2009

Pouring of concrete for the finishing of the floors of the Meeting Rm & upstairs room.
The truck bay floors pouring will happen to-morrow.

The Concrete work inside the building is now completed and
 framing has commenced on the stairs and also the washrooms

       

Framing and plumbing underway in the washrooms

       

Mechanical Rm frame up

Installation of window shutters these will protect all windows.

The brown trim on the Right-hand side
is the base for the wall cladding

       

It may appear that construction has stopped but work is proceeding with the plumbing and electrical wiring.

 

Steel Wall Cladding underway on the
remaining parts of the building.

Outer man doors have finally arrived on the 7th May however they have windows in them and should be solid for security reasons.


See Below the problem was solved

Soffit's have now been completely installed

 

Viewed from the outside Viewed from inside

Installation of Truck Bay doors has now been completed and awaiting for the operating gear to make them electrically operated with manual over ride in the event of power failure.

 

Operating gear being installed with manual override in the event of power failure.

Preparing the ground for the truck bay forecourt.

 

 
Rear Forecourt & General View

Preparing the ground for the foundation of the Rain Water collection tank
Rain Water Collection Tank Moving Day 29th, May 2009
This tank will provide water for fire tankers

Departing Dashwood

On Route

Corcan Road underpass

Corcan Road underpass - we made it!

Turning into the #2 Fire Hall Site
There is still lots of work to be done on this tank before it can become operational.
     

Getting the old blanks off in which the bolts were well rusted in place and then cleaning up all the extra protrusions.

 

Foundation slab poured for the Tanker Filling Pump expected on site about 21st June.
Water tank has received it's first coat of primer paint today July 4th
Later the same day
the final top coat of paint

Outlet flange now installed with the two valves one is for refilling,
 the other will feeding the fire pump

The Tank compound now has fencing post concreted into the ground plus security straps

Showing the anchors attachments for security straps

Fencing is completed with barb wire topping
and awaiting the gates due to-morrow 21st July.
   
  Tank Compound fencing completed  

 

Dry-walling commenced on the ceiling etc to create the fire stops

Radiant Heat and other duct work being installed.

 

 

     

Propane will be the fuel used for heating


Gas line laid from building to the propane tank


Safety Bollards installed to protect
propane tank


Propane tank arrives on site


Unloading in progress onto the pads


1000 gallon tank now in place


Tank now connected to the system

 

Excavating for Hydro and Telus Ducts

BC Hydro inspected the cable ducts this afternoon 5th May and
gave permission for back filling from the building.

Main power supply and breaker boards for the building.

June 12th, BC Hydro was on site pulling in the new main cable

Communication is very important, hence the need for a radio antenna
to connected to #1 Fire Hall, Trucks & North Island 911

Our Radio Technician doing the installing

Showing the mast head

Finally the mast and antenna

 

Cabinet work is being installed


Multi purpose coffee bar

Toilet Vanity

Meeting room Kitchen

Multi purpose room now completed

Toilets and shower now completed

Meeting Room now completed

Work Party today Saturday 4th, July to get the woodposts driven in to mark out the Parking Lot
and also to provide protection to the Septic Field to be installed next Tuesday.


Laying the posts out

Marking the depth to be driven

Driving the first post

Post driving continues

Drilling holes for top rails

Top rails going into place


C
rush rock has been added and parking lot being graded and vibrate rolling after being wetted down


Work continues on the Parking lot fencing into the late evening and we are now basically completed

 

 

Sewer System  Installation under way July 7th, 2009


Septic Tank arrives on site

Tank being lowered into the ground


Connections being made to the
distribution box

 

Another view of distribution box

 

Oil Trap from truck floor drains

The main entrance to the building work has started as of July 14th

Footings getting poured

Columns formed up.

Commencement of back fillings

Back filling completed, will now have to be compacted

Commencement of laying paving slabs

Construction of entrance canopy

The completed canopy

 

Like any major project monthly meetings take place with all concerned
to thrash out any problems or oversights

 

Tuesday 14th July

A detailed inspection was done and this time it was held in the New Meeting Room at #2 Fire Hall

Meeting Room at Dashwood #1 Fire Hall

 

Meeting Room at Dashwood #2 Fire Hall

General view of the site on

Thursday 14th, May 2009

Friday 29th, May 2009

 

Thursday 9th, July 2009

 